Grid infrastructure › Connection queue › Solar + storage

SOLAR + STORAGE · NGET

West Botley High Impact Green Energy Hub

West Botley High Impact Green Energy Hub is a 100 MW solar + storage project in planning, connecting to the National Grid (England & Wales) network at Botley West 400kV Substation, with capacity due from October 2037. The connection agreement is held by Telis Energy UK Limited.

Project stageIn planning
  1. Planning (current stage)
  2. Consented (not yet reached)
  3. Construction (not yet reached)
  4. OperatingFrom Oct 2037 (not yet reached)
  5. Closed (not yet reached)

Scoping and awaiting consents are both shown as planning. A connection agreement does not mean the project will be built: many queue projects never reach construction.

Connection details

NESO project number
PRO-004435
Customer
Telis Energy UK Limited
Technology
Demand, Energy Storage System, Nuclear, PV Array (Photo Voltaic/solar), Wind Onshore
Total capacity
100 MW
Change in this agreement
+100 MW
Capacity effective from
31 October 2037
Connection site
Botley West 400kV Substation
Transmission owner
National Grid (England & Wales)
Connection type
Direct connection to the transmission network
NESO project status
Scoping

Connection site

The connection site could not be placed on the map.

Projects connecting near Botley West · Grid map

Other projects at Botley West 400kV Substation

Source: NESO Transmission Entry Capacity (TEC) register, downloaded 8 November 2026. Contains data from NESO, licensed under the NESO Open Data Licence. Report a problem