Grid infrastructure β€Ί Connection queue β€Ί Interconnector

INTERCONNECTOR Β· SHET

GB-EU MPI

GB-EU MPI is a 1.8 GW interconnector project in planning, connecting to the SSEN Transmission (north Scotland) network at Fiddes 400kV Substation, with capacity due from October 2033. The connection agreement is held by Windgrid.

Project stageIn planning
  1. Planning (current stage)
  2. Consented (not yet reached)
  3. Construction (not yet reached)
  4. OperatingFrom Oct 2033 (not yet reached)
  5. Closed (not yet reached)

Scoping and awaiting consents are both shown as planning. A connection agreement does not mean the project will be built: many queue projects never reach construction.

Connection details

NESO project number
PRO-004398
Customer
Windgrid
Technology
Interconnector
Export capacity
1.8 GW
Import capacity
1.8 GW
Change in this agreement
+1.8 GW
Capacity effective from
31 October 2033
Connection site
Fiddes 400kV Substation
Transmission owner
SSEN Transmission (north Scotland)
Connection type
Interconnector
NESO project status
Scoping
Connections reform gate
Gate 1

Connection site

The marker shows the connection substation, not the project itself, with the transmission network around it.

Projects connecting near Fiddes Β· Grid map

Source: NESO interconnector register, downloaded 8 November 2026. Contains data from NESO, licensed under the NESO Open Data Licence. Report a problem