Grid infrastructure βΊ Connection queue βΊ Battery storage
BATTERY STORAGE Β· SPTKennishead
Kennishead is a 40 MW battery storage project in planning, connecting to the SP Transmission (south Scotland) network at Haggs Road GSP, with capacity due from October 2031. The connection agreement is held by Starlight Energy UK Limited.
- Planning (current stage)
- Consented (not yet reached)
- Construction (not yet reached)
- OperatingFrom Oct 2031 (not yet reached)
- Closed (not yet reached)
Scoping and awaiting consents are both shown as planning. A connection agreement does not mean the project will be built: many queue projects never reach construction.
Connection details
- NESO project number
- PRO-004373
- Customer
- Starlight Energy UK Limited
- Technology
- Energy Storage System
- Total capacity
- 40 MW
- Change in this agreement
- +40 MW
- Capacity effective from
- 31 October 2031
- Connection site
- Haggs Road GSP
- Transmission owner
- SP Transmission (south Scotland)
- Connection type
- Embedded (connects through the local distribution network)
- NESO project status
- Scoping
- Connections reform gate
- Gate 1
Connection site
The marker shows the connection substation, not the project itself, with the transmission network around it.
Source: NESO Transmission Entry Capacity (TEC) register, downloaded 8 November 2026. Contains data from NESO, licensed under the NESO Open Data Licence. Report a problem