Contullich BESS

Contullich BESS is a 45 MW battery storage project in planning, connecting to the SSEN Transmission (north Scotland) network at Alness 2 275/33 kV GSP Substation, with capacity due from October 2030. The connection agreement is held by Contullich Energy Storage Limited.

Project stageIn planning
  1. Planning (current stage)
  2. Consented (not yet reached)
  3. Construction (not yet reached)
  4. OperatingFrom Oct 2030 (not yet reached)
  5. Closed (not yet reached)

Scoping and awaiting consents are both shown as planning. A connection agreement does not mean the project will be built: many queue projects never reach construction.

Connection details

NESO project number
PRO-004300
Customer
Contullich Energy Storage Limited
Technology
Energy Storage System
Total capacity
45 MW
Change in this agreement
+45 MW
Capacity effective from
31 October 2030
Connection site
Alness 2 275/33 kV GSP Substation
Transmission owner
SSEN Transmission (north Scotland)
Connection type
Embedded (connects through the local distribution network)
NESO project status
Scoping

Connection site

The marker shows the connection substation, not the project itself, with the transmission network around it.

Projects connecting near Alness · Grid map

Other projects at Alness 2 275/33 kV GSP Substation

Source: NESO Transmission Entry Capacity (TEC) register, downloaded 8 November 2026. Contains data from NESO, licensed under the NESO Open Data Licence. Report a problem