BATTERY STORAGE Β· SHETStrichen North BESS
Strichen North BESS is a 25 MW battery storage project in planning, connecting to the SSEN Transmission (north Scotland) network at Strichen GSP, with capacity due from October 2033. The connection agreement is held by Muirden Energy LLP.
- Planning (current stage)
- Consented (not yet reached)
- Construction (not yet reached)
- OperatingFrom Oct 2033 (not yet reached)
- Closed (not yet reached)
Scoping and awaiting consents are both shown as planning. A connection agreement does not mean the project will be built: many queue projects never reach construction.
Connection details
- NESO project number
- PRO-004177
- Customer
- Muirden Energy LLP
- Technology
- Energy Storage System
- Total capacity
- 25 MW
- Change in this agreement
- +25 MW
- Capacity effective from
- 31 October 2033
- Connection site
- Strichen GSP
- Transmission owner
- SSEN Transmission (north Scotland)
- Connection type
- Embedded (connects through the local distribution network)
- NESO project status
- Scoping
Connection site
The marker shows the connection substation, not the project itself, with the transmission network around it.
Source: NESO Transmission Entry Capacity (TEC) register, downloaded 8 November 2026. Contains data from NESO, licensed under the NESO Open Data Licence. Report a problem