Grid infrastructure › Connection queue › Battery storage
BATTERY STORAGE · NGET014 NEP Bransholme
014 NEP Bransholme is a 40 MW battery storage project in planning, connecting to the National Grid (England & Wales) network at North Humber Connection Node C 132kV Substation, with capacity due from October 2035. The connection agreement is held by New Energy Partnership Limited.
- Planning (current stage)
- Consented (not yet reached)
- Construction (not yet reached)
- OperatingFrom Oct 2035 (not yet reached)
- Closed (not yet reached)
Scoping and awaiting consents are both shown as planning. A connection agreement does not mean the project will be built: many queue projects never reach construction.
Connection details
- NESO project number
- PRO-004043
- Customer
- New Energy Partnership Limited
- Technology
- Energy Storage System
- Total capacity
- 40 MW
- Change in this agreement
- +40 MW
- Capacity effective from
- 30 October 2035
- Connection site
- North Humber Connection Node C 132kV Substation
- Transmission owner
- National Grid (England & Wales)
- Connection type
- Embedded (connects through the local distribution network)
- NESO project status
- Scoping
Connection site
This project connects at a new substation (a “connection node”) that has not been built or located yet.
Projects connecting near North Humber Connection Node C · Grid map
Source: NESO Transmission Entry Capacity (TEC) register, downloaded 8 November 2026. Contains data from NESO, licensed under the NESO Open Data Licence. Report a problem