SOLAR + STORAGE · NGET

Bramford GEC (Ethos Green)

Bramford GEC (Ethos Green) is a 650 MW solar + storage project in planning, connecting to the National Grid (England & Wales) network at Bramford B 400kV Substation, with capacity due from June 2032. The connection agreement is held by Bramford Green Energy Centre Ltd.

Project stageIn planning
  1. Planning (current stage)
  2. Consented (not yet reached)
  3. Construction (not yet reached)
  4. OperatingFrom Jun 2032 (not yet reached)
  5. Closed (not yet reached)

Scoping and awaiting consents are both shown as planning. A connection agreement does not mean the project will be built: many queue projects never reach construction.

Connection details

NESO project number
PRO-004027
Customer
Bramford Green Energy Centre Ltd
Technology
Energy Storage System, PV Array (Photo Voltaic/solar)
Total capacity
650 MW
Change in this agreement
+650 MW
Capacity effective from
1 June 2032
Connection site
Bramford B 400kV Substation
Transmission owner
National Grid (England & Wales)
Connection type
Direct connection to the transmission network
NESO project status
Awaiting Consents
Connections reform gate
Gate 1

Connection site

The marker shows the connection substation, not the project itself, with the transmission network around it.

Projects connecting near Bramford B · Grid map

Source: NESO Transmission Entry Capacity (TEC) register, downloaded 8 November 2026. Contains data from NESO, licensed under the NESO Open Data Licence. Report a problem