Grid infrastructure βΊ Connection queue βΊ Battery storage
BATTERY STORAGE Β· NGETEnderby BESS
Enderby BESS is a 250 MW battery storage project in planning, connecting to the National Grid (England & Wales) network at Earl Shilton 400kV Substation, with capacity due from November 2033. The connection agreement is held by Earl Shilton Energy Park Limited.
- Planning (current stage)
- Consented (not yet reached)
- Construction (not yet reached)
- OperatingFrom Nov 2033 (not yet reached)
- Closed (not yet reached)
Scoping and awaiting consents are both shown as planning. A connection agreement does not mean the project will be built: many queue projects never reach construction.
Connection details
- NESO project number
- PRO-003872
- Customer
- Earl Shilton Energy Park Limited
- Technology
- Energy Storage System
- Total capacity
- 250 MW
- Change in this agreement
- +250 MW
- Capacity effective from
- 30 November 2033
- Connection site
- Earl Shilton 400kV Substation
- Transmission owner
- National Grid (England & Wales)
- Connection type
- Direct connection to the transmission network
- NESO project status
- Scoping
- Connections reform gate
- Gate 1
Connection site
The marker shows the place the connection site is named after, not the project itself, with the transmission network around it.
Other projects at Earl Shilton 400kV Substation
Source: NESO Transmission Entry Capacity (TEC) register, downloaded 8 November 2026. Contains data from NESO, licensed under the NESO Open Data Licence. Report a problem