Grid infrastructure › Connection queue › Battery storage
BATTERY STORAGE · NGETRed House Farm - Friston 400kV 249MW connection
Red House Farm - Friston 400kV 249MW connection is a 249 MW battery storage project in planning, connecting to the National Grid (England & Wales) network at South Anglia Connection Node E 400kV Substation, with capacity due from October 2034. The connection agreement is held by Cambridge Power Limited.
- Planning (current stage)
- Consented (not yet reached)
- Construction (not yet reached)
- OperatingFrom Oct 2034 (not yet reached)
- Closed (not yet reached)
Scoping and awaiting consents are both shown as planning. A connection agreement does not mean the project will be built: many queue projects never reach construction.
Connection details
- NESO project number
- PRO-003787
- Customer
- Cambridge Power Limited
- Technology
- Energy Storage System
- Total capacity
- 249 MW
- Change in this agreement
- +249 MW
- Capacity effective from
- 31 October 2034
- Connection site
- South Anglia Connection Node E 400kV Substation
- Transmission owner
- National Grid (England & Wales)
- Connection type
- Direct connection to the transmission network
- NESO project status
- Scoping
Connection site
This project connects at a new substation (a “connection node”) that has not been built or located yet.
Projects connecting near South Anglia Connection Node E · Grid map
Other projects at South Anglia Connection Node E 400kV Substation
Source: NESO Transmission Entry Capacity (TEC) register, downloaded 8 November 2026. Contains data from NESO, licensed under the NESO Open Data Licence. Report a problem