Grid infrastructure › Connection queue › Solar + storage

SOLAR + STORAGE · SPT

Whiteminhill Renewable Energy Park

Whiteminhill Renewable Energy Park is a 220 MW solar + storage project in planning, connecting to the SP Transmission (south Scotland) network at Whiteminhill 275/33kV Substation, with capacity due from October 2036. The connection agreement is held by Voltalia UK Ltd.

Project stageIn planning
  1. Planning (current stage)
  2. Consented (not yet reached)
  3. Construction (not yet reached)
  4. OperatingFrom Oct 2036 (not yet reached)
  5. Closed (not yet reached)

Scoping and awaiting consents are both shown as planning. A connection agreement does not mean the project will be built: many queue projects never reach construction.

Connection details

NESO project number
PRO-003693
Customer
Voltalia UK Ltd
Technology
Energy Storage System, PV Array (Photo Voltaic/solar), Wind Onshore
Total capacity
220 MW
Change in this agreement
+220 MW
Capacity effective from
31 October 2036
Connection site
Whiteminhill 275/33kV Substation
Transmission owner
SP Transmission (south Scotland)
Connection type
Direct connection to the transmission network
NESO project status
Scoping

Connection site

The connection site could not be placed on the map.

Projects connecting near Whiteminhill · Grid map

Source: NESO Transmission Entry Capacity (TEC) register, downloaded 8 November 2026. Contains data from NESO, licensed under the NESO Open Data Licence. Report a problem