Grid infrastructure βΊ Connection queue βΊ Battery storage
BATTERY STORAGE Β· SPTGlasgow Road 40MW BESS
Glasgow Road 40MW BESS is a 40 MW battery storage project in planning, connecting to the SP Transmission (south Scotland) network at Giffnock 275/33kV, with capacity due from October 2028. The connection agreement is held by GPC 1137 Ltd.
- Planning (current stage)
- Consented (not yet reached)
- Construction (not yet reached)
- OperatingFrom Oct 2028 (not yet reached)
- Closed (not yet reached)
Scoping and awaiting consents are both shown as planning. A connection agreement does not mean the project will be built: many queue projects never reach construction.
Connection details
- NESO project number
- PRO-003566
- Customer
- GPC 1137 Ltd
- Technology
- Energy Storage System
- Total capacity
- 40 MW
- Change in this agreement
- +40 MW
- Capacity effective from
- 31 October 2028
- Connection site
- Giffnock 275/33kV
- Transmission owner
- SP Transmission (south Scotland)
- Connection type
- Embedded (connects through the local distribution network)
- NESO project status
- Scoping
Connection site
The marker shows the connection substation, not the project itself, with the transmission network around it.
Source: NESO Transmission Entry Capacity (TEC) register, downloaded 8 November 2026. Contains data from NESO, licensed under the NESO Open Data Licence. Report a problem