Grid infrastructure βΊ Connection queue βΊ Battery storage
BATTERY STORAGE Β· SPTGilbertfield Farm BESS
Gilbertfield Farm BESS is a 40 MW battery storage project in planning, connecting to the SP Transmission (south Scotland) network at Clydesmill GSP, with capacity due from April 2029. The connection agreement is held by GPC 678 LTD.
Project stageIn planning
- Planning (current stage)
- Consented (not yet reached)
- Construction (not yet reached)
- OperatingFrom Apr 2029 (not yet reached)
- Closed (not yet reached)
Scoping and awaiting consents are both shown as planning. A connection agreement does not mean the project will be built: many queue projects never reach construction.
Connection details
- NESO project number
- PRO-003564
- Customer
- GPC 678 LTD
- Technology
- Energy Storage System
- Total capacity
- 40 MW
- Change in this agreement
- +40 MW
- Capacity effective from
- 30 April 2029
- Connection site
- Clydesmill GSP
- Transmission owner
- SP Transmission (south Scotland)
- Connection type
- Embedded (connects through the local distribution network)
- NESO project status
- Scoping
Connection site
The connection site could not be placed on the map.
Source: NESO Transmission Entry Capacity (TEC) register, downloaded 8 November 2026. Contains data from NESO, licensed under the NESO Open Data Licence. Report a problem