Grid infrastructure › Connection queue › Onshore wind
ONSHORE WIND · SPTBankend Rig III Wind Farm
Bankend Rig III Wind Farm is a 78 MW onshore wind project in planning, connecting to the SP Transmission (south Scotland) network at Bankend Rig III 132kV Collector Substation, with capacity due from April 2030. The connection agreement is held by Wilson Renewables III LLP.
- Planning (current stage)
- Consented (not yet reached)
- Construction (not yet reached)
- OperatingFrom Apr 2030 (not yet reached)
- Closed (not yet reached)
Scoping and awaiting consents are both shown as planning. A connection agreement does not mean the project will be built: many queue projects never reach construction.
Connection details
- NESO project number
- PRO-003451
- Customer
- Wilson Renewables III LLP
- Technology
- Wind Onshore
- Total capacity
- 78 MW
- Change in this agreement
- +78 MW
- Capacity effective from
- 30 April 2030
- Connection site
- Bankend Rig III 132kV Collector Substation
- Transmission owner
- SP Transmission (south Scotland)
- Connection type
- Direct connection to the transmission network
- NESO project status
- Scoping
Connection site
The connection site could not be placed on the map.
Source: NESO Transmission Entry Capacity (TEC) register, downloaded 8 November 2026. Contains data from NESO, licensed under the NESO Open Data Licence. Report a problem