ONSHORE WIND · SHETGrimshader Wind Farm
Grimshader Wind Farm is a 79 MW onshore wind project in planning, connecting to the SSEN Transmission (north Scotland) network at Grimshader Wind Farm Substation132 KV, with capacity due from October 2033. The connection agreement is held by RWE Renewables UK Onshore Wind Limited.
- Planning (current stage)
- Consented (not yet reached)
- Construction (not yet reached)
- OperatingFrom Oct 2033 (not yet reached)
- Closed (not yet reached)
Scoping and awaiting consents are both shown as planning. A connection agreement does not mean the project will be built: many queue projects never reach construction.
Connection details
- NESO project number
- PRO-003258
- Customer
- RWE Renewables UK Onshore Wind Limited
- Technology
- Wind Onshore
- Total capacity
- 79 MW
- Change in this agreement
- +79 MW
- Capacity effective from
- 31 October 2033
- Connection site
- Grimshader Wind Farm Substation132 KV
- Transmission owner
- SSEN Transmission (north Scotland)
- Connection type
- Direct connection to the transmission network
- NESO project status
- Scoping
- Connections reform gate
- Gate 1
Connection site
The connection site could not be placed on the map.
Projects connecting near Grimshader Wind Farm Substation · Grid map
Source: NESO Transmission Entry Capacity (TEC) register, downloaded 8 November 2026. Contains data from NESO, licensed under the NESO Open Data Licence. Report a problem