Glenrothes Hybrid BESS & Solar PV

Glenrothes Hybrid BESS & Solar PV is a 200 MW solar + storage project in planning, connecting to the SP Transmission (south Scotland) network at Conland Substation, with capacity due from October 2031. The connection agreement is held by Tagenergy Development UK Limited.

Project stageIn planning
  1. Planning (current stage)
  2. Consented (not yet reached)
  3. Construction (not yet reached)
  4. OperatingFrom Oct 2031 (not yet reached)
  5. Closed (not yet reached)

Scoping and awaiting consents are both shown as planning. A connection agreement does not mean the project will be built: many queue projects never reach construction.

Connection details

NESO project number
PRO-003252
Customer
Tagenergy Development UK Limited
Technology
Energy Storage System, PV Array (Photo Voltaic/solar)
Total capacity
200 MW
Change in this agreement
+200 MW
Capacity effective from
30 October 2031
Connection site
Conland Substation
Transmission owner
SP Transmission (south Scotland)
Connection type
Direct connection to the transmission network
NESO project status
Scoping
Connections reform gate
Gate 1

Connection site

The connection site could not be placed on the map.

Projects connecting near Conland Substation · Grid map

Other projects at Conland Substation

Source: NESO Transmission Entry Capacity (TEC) register, downloaded 8 November 2026. Contains data from NESO, licensed under the NESO Open Data Licence. Report a problem