Grid infrastructure › Connection queue › Solar + storage
SOLAR + STORAGE · SPTGlenrothes Hybrid BESS & Solar PV
Glenrothes Hybrid BESS & Solar PV is a 200 MW solar + storage project in planning, connecting to the SP Transmission (south Scotland) network at Conland Substation, with capacity due from October 2031. The connection agreement is held by Tagenergy Development UK Limited.
- Planning (current stage)
- Consented (not yet reached)
- Construction (not yet reached)
- OperatingFrom Oct 2031 (not yet reached)
- Closed (not yet reached)
Scoping and awaiting consents are both shown as planning. A connection agreement does not mean the project will be built: many queue projects never reach construction.
Connection details
- NESO project number
- PRO-003252
- Customer
- Tagenergy Development UK Limited
- Technology
- Energy Storage System, PV Array (Photo Voltaic/solar)
- Total capacity
- 200 MW
- Change in this agreement
- +200 MW
- Capacity effective from
- 30 October 2031
- Connection site
- Conland Substation
- Transmission owner
- SP Transmission (south Scotland)
- Connection type
- Direct connection to the transmission network
- NESO project status
- Scoping
- Connections reform gate
- Gate 1
Connection site
The connection site could not be placed on the map.
Other projects at Conland Substation
Source: NESO Transmission Entry Capacity (TEC) register, downloaded 8 November 2026. Contains data from NESO, licensed under the NESO Open Data Licence. Report a problem