Grid infrastructure › Connection queue › Battery storage
BATTERY STORAGE · SPTGH DEVCO Kincardine BESS
GH DEVCO Kincardine BESS is a 42 MW battery storage project in planning, connecting to the SP Transmission (south Scotland) network at GH DEVCO KINCARDINE BESS 132kV SUBSTATION, with capacity due from October 2029. The connection agreement is held by Kincardine Storage Limited.
- Planning (current stage)
- Consented (not yet reached)
- Construction (not yet reached)
- OperatingFrom Oct 2029 (not yet reached)
- Closed (not yet reached)
Scoping and awaiting consents are both shown as planning. A connection agreement does not mean the project will be built: many queue projects never reach construction.
Connection details
- NESO project number
- PRO-003173
- Customer
- Kincardine Storage Limited
- Technology
- Energy Storage System
- Total capacity
- 42 MW
- Change in this agreement
- +42 MW
- Capacity effective from
- 31 October 2029
- Connection site
- GH DEVCO KINCARDINE BESS 132kV SUBSTATION
- Transmission owner
- SP Transmission (south Scotland)
- Connection type
- Direct connection to the transmission network
- NESO project status
- Scoping
Connection site
The connection site could not be placed on the map.
Projects connecting near GH DEVCO KINCARDINE BESS · Grid map
Source: NESO Transmission Entry Capacity (TEC) register, downloaded 8 November 2026. Contains data from NESO, licensed under the NESO Open Data Licence. Report a problem