Grid infrastructure › Connection queue › Battery storage

BATTERY STORAGE · NGET

Beddington 1 BESS

Beddington 1 BESS is a 240 MW battery storage project in planning, connecting to the National Grid (England & Wales) network at London South Connection Node A 132kV Substation, with capacity due from October 2037. The connection agreement is held by Bluestone Beddington 1 Ltd.

Project stageIn planning
  1. Planning (current stage)
  2. Consented (not yet reached)
  3. Construction (not yet reached)
  4. OperatingFrom Oct 2037 (not yet reached)
  5. Closed (not yet reached)

Scoping and awaiting consents are both shown as planning. A connection agreement does not mean the project will be built: many queue projects never reach construction.

Connection details

NESO project number
PRO-003170
Customer
Bluestone Beddington 1 Ltd
Technology
Energy Storage System
Total capacity
240 MW
Change in this agreement
+240 MW
Capacity effective from
31 October 2037
Connection site
London South Connection Node A 132kV Substation
Transmission owner
National Grid (England & Wales)
Connection type
Embedded (connects through the local distribution network)
NESO project status
Scoping
Connections reform gate
Gate 1

Connection site

This project connects at a new substation (a “connection node”) that has not been built or located yet.

Projects connecting near London South Connection Node A · Grid map

Other projects at London South Connection Node A 132kV Substation

Source: NESO Transmission Entry Capacity (TEC) register, downloaded 8 November 2026. Contains data from NESO, licensed under the NESO Open Data Licence. Report a problem