ONSHORE WIND Β· SPTPenninghame Wind Farm
Penninghame Wind Farm is a 60 MW onshore wind project in planning, connecting to the SP Transmission (south Scotland) network at Penninghame Substation, with capacity due from October 2031. The connection agreement is held by Edf Energy Renewables Limited.
- Planning (current stage)
- Consented (not yet reached)
- Construction (not yet reached)
- OperatingFrom Oct 2031 (not yet reached)
- Closed (not yet reached)
Scoping and awaiting consents are both shown as planning. A connection agreement does not mean the project will be built: many queue projects never reach construction.
Connection details
- NESO project number
- PRO-002830
- Customer
- Edf Energy Renewables Limited
- Technology
- Wind Onshore
- Total capacity
- 60 MW
- Change in this agreement
- +60 MW
- Capacity effective from
- 31 October 2031
- Connection site
- Penninghame Substation
- Transmission owner
- SP Transmission (south Scotland)
- Connection type
- Direct connection to the transmission network
- NESO project status
- Scoping
- Connections reform gate
- Gate 1
Connection site
The marker shows the place the connection site is named after, not the project itself, with the transmission network around it.
Source: NESO Transmission Entry Capacity (TEC) register, downloaded 8 November 2026. Contains data from NESO, licensed under the NESO Open Data Licence. Report a problem