Grid infrastructure › Connection queue › Onshore wind
ONSHORE WIND · SPTCraighead Wind Farm
Craighead Wind Farm is a 77 MW onshore wind project in planning, connecting to the SP Transmission (south Scotland) network at CRAIGHEAD WIND FARM 132kV SUBSTATION, with capacity due from October 2032. The connection agreement is held by Galileo 02 Limited.
- Planning (current stage)
- Consented (not yet reached)
- Construction (not yet reached)
- OperatingFrom Oct 2032 (not yet reached)
- Closed (not yet reached)
Scoping and awaiting consents are both shown as planning. A connection agreement does not mean the project will be built: many queue projects never reach construction.
Connection details
- NESO project number
- PRO-002821
- Customer
- Galileo 02 Limited
- Technology
- Wind Onshore
- Total capacity
- 77 MW
- Change in this agreement
- +77 MW
- Capacity effective from
- 29 October 2032
- Connection site
- CRAIGHEAD WIND FARM 132kV SUBSTATION
- Transmission owner
- SP Transmission (south Scotland)
- Connection type
- Direct connection to the transmission network
- NESO project status
- Scoping
- Connections reform gate
- Gate 1
Connection site
The marker shows the place the connection site is named after, not the project itself, with the transmission network around it.
Source: NESO Transmission Entry Capacity (TEC) register, downloaded 8 November 2026. Contains data from NESO, licensed under the NESO Open Data Licence. Report a problem