Grid infrastructure › Connection queue › Battery storage
BATTERY STORAGE · SPTDrumfad Battery Storage System
Drumfad Battery Storage System is a 40 MW battery storage project consented, connecting to the SP Transmission (south Scotland) network at Helensburgh 132/33kV, with capacity due from October 2027. The connection agreement is held by Eku Energy Faune Projects (UK) Limited.
Project stageConsented
- Planning (completed)
- Consented (current stage)
- Construction (not yet reached)
- OperatingFrom Oct 2027 (not yet reached)
- Closed (not yet reached)
Connection details
- NESO project number
- PRO-002419
- Customer
- Eku Energy Faune Projects (UK) Limited
- Technology
- Energy Storage System
- Total capacity
- 40 MW
- Change in this agreement
- +40 MW
- Capacity effective from
- 29 October 2027
- Connection site
- Helensburgh 132/33kV
- Transmission owner
- SP Transmission (south Scotland)
- Connection type
- Embedded (connects through the local distribution network)
- NESO project status
- Consents Approved
- Connections reform gate
- Gate 2
Connection site
The marker shows the connection substation, not the project itself, with the transmission network around it.
Source: NESO Transmission Entry Capacity (TEC) register, downloaded 8 November 2026. Contains data from NESO, licensed under the NESO Open Data Licence. Report a problem