Grid infrastructure › Connection queue › Battery storage

BATTERY STORAGE · SPT

Scottish Water Bonnybridge STW 60MW BESS

Scottish Water Bonnybridge STW 60MW BESS is a 60 MW battery storage project in planning, connecting to the SP Transmission (south Scotland) network at Bonnybridge 132/33kV, with capacity due from October 2030. The connection agreement is held by Bluestone Energy Ltd.

Project stageIn planning
  1. Planning (current stage)
  2. Consented (not yet reached)
  3. Construction (not yet reached)
  4. OperatingFrom Oct 2030 (not yet reached)
  5. Closed (not yet reached)

Scoping and awaiting consents are both shown as planning. A connection agreement does not mean the project will be built: many queue projects never reach construction.

Connection details

NESO project number
PRO-002410
Customer
Bluestone Energy Ltd
Technology
Energy Storage System
Total capacity
60 MW
Change in this agreement
+60 MW
Capacity effective from
31 October 2030
Connection site
Bonnybridge 132/33kV
Transmission owner
SP Transmission (south Scotland)
Connection type
Embedded (connects through the local distribution network)
NESO project status
Scoping
Connections reform gate
Gate 1

Connection site

The marker shows the connection substation, not the project itself, with the transmission network around it.

Projects connecting near Bonnybridge · Grid map

Other projects at Bonnybridge 132/33kV