Grid infrastructure › Connection queue › Onshore wind
ONSHORE WIND · SHETAbhainn Dubh Wind Farm
Abhainn Dubh Wind Farm is a 75 MW onshore wind project in planning, connecting to the SSEN Transmission (north Scotland) network at Abhainn Dubh Wind Farm 132kV Substation, with capacity due from May 2029. The connection agreement is held by E Power Limited.
- Planning (current stage)
- Consented (not yet reached)
- Construction (not yet reached)
- OperatingFrom May 2029 (not yet reached)
- Closed (not yet reached)
Scoping and awaiting consents are both shown as planning. A connection agreement does not mean the project will be built: many queue projects never reach construction.
Connection details
- NESO project number
- PRO-002272
- Customer
- E Power Limited
- Technology
- Wind Onshore
- Total capacity
- 75 MW
- Change in this agreement
- +75 MW
- Capacity effective from
- 31 May 2029
- Connection site
- Abhainn Dubh Wind Farm 132kV Substation
- Transmission owner
- SSEN Transmission (north Scotland)
- Connection type
- Direct connection to the transmission network
- NESO project status
- Scoping
- Connections reform gate
- Gate 1
Connection site
The connection site could not be placed on the map.
Source: NESO Transmission Entry Capacity (TEC) register, downloaded 8 November 2026. Contains data from NESO, licensed under the NESO Open Data Licence. Report a problem