Grid infrastructure › Connection queue › Solar + storage
SOLAR + STORAGE · NGETBraybrooke Solar and Battery Connection
Braybrooke Solar and Battery Connection is a 500 MW solar + storage project in planning, connecting to the National Grid (England & Wales) network at Braybrooke (Network Rail) GSP, with capacity due from October 2031. The connection agreement is held by Irena BESS LIMITED.
- Planning (current stage)
- Consented (not yet reached)
- Construction (not yet reached)
- OperatingFrom Oct 2031 (not yet reached)
- Closed (not yet reached)
Scoping and awaiting consents are both shown as planning. A connection agreement does not mean the project will be built: many queue projects never reach construction.
Connection details
- NESO project number
- PRO-002207
- Customer
- Irena BESS LIMITED
- Technology
- Energy Storage System, PV Array (Photo Voltaic/solar)
- Total capacity
- 500 MW
- Change in this agreement
- +500 MW
- Capacity effective from
- 31 October 2031
- Connection site
- Braybrooke (Network Rail) GSP
- Transmission owner
- National Grid (England & Wales)
- Connection type
- Direct connection to the transmission network
- NESO project status
- Scoping
Connection site
The marker shows the place the connection site is named after, not the project itself, with the transmission network around it.
Projects connecting near Braybrooke (Network Rail) GSP · Grid map
Source: NESO Transmission Entry Capacity (TEC) register, downloaded 8 November 2026. Contains data from NESO, licensed under the NESO Open Data Licence. Report a problem