Grid infrastructure › Connection queue › Battery storage

BATTERY STORAGE · SPT

Bankside BESS

Bankside BESS is a 43 MW battery storage project under construction or commissioning, connecting to the SP Transmission (south Scotland) network at Bainsford 132/33kV, with capacity due from November 2025. The connection agreement is held by Falkirk Power Ltd.

Project stageUnder construction
  1. Planning (completed)
  2. Consented (completed)
  3. Construction (current stage)
  4. OperatingFrom Nov 2025 (not yet reached)
  5. Closed (not yet reached)

Connection details

NESO project number
PRO-002151
Customer
Falkirk Power Ltd
Technology
Energy Storage System
Total capacity
43 MW
Change in this agreement
+43 MW
Capacity effective from
24 November 2025
Connection site
Bainsford 132/33kV
Transmission owner
SP Transmission (south Scotland)
Connection type
Embedded (connects through the local distribution network)
NESO project status
Under Construction/Commissioning
Connections reform gate
Gate 2

Connection site

The marker shows the connection substation, not the project itself, with the transmission network around it.

Projects connecting near Bainsford · Grid map

Source: NESO Transmission Entry Capacity (TEC) register, downloaded 8 November 2026. Contains data from NESO, licensed under the NESO Open Data Licence. Report a problem