Grid infrastructure β€Ί Connection queue β€Ί Onshore wind

ONSHORE WIND Β· SPT

Borders Wind Farm

Borders Wind Farm is a 400 MW onshore wind project in planning, connecting to the SP Transmission (south Scotland) network at Borders Windfarm 132kV, with capacity due from May 2033. The connection agreement is held by Edf Energy Renewables Limited.

Project stageIn planning
  1. Planning (current stage)
  2. Consented (not yet reached)
  3. Construction (not yet reached)
  4. OperatingFrom May 2033 (not yet reached)
  5. Closed (not yet reached)

Scoping and awaiting consents are both shown as planning. A connection agreement does not mean the project will be built: many queue projects never reach construction.

Connection details

NESO project number
PRO-001977
Customer
Edf Energy Renewables Limited
Technology
Wind Onshore
Total capacity
400 MW
Change in this agreement
+400 MW
Capacity effective from
30 May 2033
Connection site
Borders Windfarm 132kV
Transmission owner
SP Transmission (south Scotland)
Connection type
Direct connection to the transmission network
NESO project status
Scoping
Connections reform gate
Gate 1

Connection site

The connection site could not be placed on the map.

Projects connecting near Borders Windfarm Β· Grid map