OFFSHORE WIND · NGETCeltic Offshore Wind Farm
Celtic Offshore Wind Farm is a 400 MW offshore wind project in planning, connecting to the National Grid (England & Wales) network at Rwe Celtic Offshore Substation, with capacity due from October 2031. The connection agreement is held by RWE Offshore Wind.
- Planning (current stage)
- Consented (not yet reached)
- Construction (not yet reached)
- OperatingFrom Oct 2031 (not yet reached)
- Closed (not yet reached)
Scoping and awaiting consents are both shown as planning. A connection agreement does not mean the project will be built: many queue projects never reach construction.
Connection details
- NESO project number
- PRO-001760
- Customer
- RWE Offshore Wind
- Technology
- Wind Offshore
- Total capacity
- 400 MW
- Change in this agreement
- +400 MW
- Capacity effective from
- 31 October 2031
- Connection site
- Rwe Celtic Offshore Substation
- Transmission owner
- National Grid (England & Wales)
- Connection type
- Direct connection to the transmission network
- NESO project status
- Scoping
- Connections reform gate
- Gate 1
Connection site
The connection site could not be placed on the map.
Projects connecting near Rwe Celtic Offshore Substation · Grid map
Source: NESO Transmission Entry Capacity (TEC) register, downloaded 8 November 2026. Contains data from NESO, licensed under the NESO Open Data Licence. Report a problem