Elvanfoot (9.8 MW) Energy Storage is a 9.8 MW battery storage project consented, connecting to the SP Transmission (south Scotland) network at Elvanfoot 400/275/33kV, with capacity due from April 2027. The connection agreement is held by Elvanfoot Energy Storage Limited.
Project stageConsented
- Planning (completed)
- Consented (current stage)
- Construction (not yet reached)
- OperatingFrom Apr 2027 (not yet reached)
- Closed (not yet reached)
Connection details
- NESO project number
- PRO-001721
- Customer
- Elvanfoot Energy Storage Limited
- Technology
- Energy Storage System
- Total capacity
- 9.8 MW
- Change in this agreement
- +9.8 MW
- Capacity effective from
- 30 April 2027
- Connection site
- Elvanfoot 400/275/33kV
- Transmission owner
- SP Transmission (south Scotland)
- Connection type
- Direct connection to the transmission network
- NESO project status
- Consents Approved
- Connections reform gate
- Gate 2
Connection site
The marker shows the connection substation, not the project itself, with the transmission network around it.