Grid infrastructure β€Ί Connection queue β€Ί Solar + storage

SOLAR + STORAGE Β· NGET

Somerford

Somerford is a 48 MW solar + storage project consented, connecting to the National Grid (England & Wales) network at Minety 400kV Substation, with capacity due from June 2025. The connection agreement is held by PD688IRO LTD.

Project stageConsented
  1. Planning (completed)
  2. Consented (current stage)
  3. Construction (not yet reached)
  4. OperatingFrom Jun 2025 (not yet reached)
  5. Closed (not yet reached)

Connection details

NESO project number
PRO-001631
Customer
PD688IRO LTD
Technology
Energy Storage System, PV Array (Photo Voltaic/solar)
Total capacity
48 MW
Change in this agreement
+48 MW
Capacity effective from
30 June 2025
Connection site
Minety 400kV Substation
Transmission owner
National Grid (England & Wales)
Connection type
Direct connection to the transmission network
NESO project status
Consents Approved

Connection site

The marker shows the connection substation, not the project itself, with the transmission network around it.

Projects connecting near Minety Β· Grid map

Other projects at Minety 400kV Substation

Source: NESO Transmission Entry Capacity (TEC) register, downloaded 8 November 2026. Contains data from NESO, licensed under the NESO Open Data Licence. Report a problem