🔌 EV Partnership Switch to Octopus Energy & unlock exclusive smart EV charging rates Find out more → Skip to main content

Grid infrastructure › Connection queue › Battery storage

BATTERY STORAGE · SPT

Coylton 275kV Greener Grid Park

Coylton 275kV Greener Grid Park is a 450 MW battery storage project in planning, connecting to the SP Transmission (south Scotland) network at Coylton 275kV substation, with capacity due from October 2037. The connection agreement is held by Coylton Energy Limited.

Project stageIn planning
  1. Planning (current stage)
  2. Consented (not yet reached)
  3. Construction (not yet reached)
  4. OperatingFrom Oct 2037 (not yet reached)
  5. Closed (not yet reached)

Scoping and awaiting consents are both shown as planning. A connection agreement does not mean the project will be built: many queue projects never reach construction.

Connection details

NESO project number
PRO-001551-3
Customer
Coylton Energy Limited
Technology
Energy Storage System
Total capacity
450 MW
Change in this agreement
+300 MW
Capacity effective from
30 October 2037
Connection site
Coylton 275kV substation
Transmission owner
SP Transmission (south Scotland)
Connection type
Direct connection to the transmission network
NESO project status
Scoping

Connection site

The marker shows the connection substation, not the project itself, with the transmission network around it.

Projects connecting near Coylton · Grid map

Other projects at Coylton 275kV substation

Source: NESO Transmission Entry Capacity (TEC) register, downloaded 8 November 2026. Contains data from NESO, licensed under the NESO Open Data Licence. Report a problem