πŸ”Œ EV Partnership Switch to Octopus Energy & unlock exclusive smart EV charging rates Find out more β†’ Skip to main content

Grid infrastructure β€Ί Connection queue β€Ί Gas

GAS Β· NGET

Kemsley

Kemsley is a 36 MW gas project built and connected, connecting to the National Grid (England & Wales) network at Kemsley GSP. The connection agreement is held by Grovehurst Energy Limited.

Project stageOperating
  1. Planning (completed)
  2. Consented (completed)
  3. Construction (completed)
  4. Operating (current stage)
  5. Closed (not yet reached)

Connection details

NESO project number
PRO-001328
Customer
Grovehurst Energy Limited
Technology
CHP (Combined Heat and Power)
Total capacity
36 MW
Already connected
36 MW
Connection site
Kemsley GSP
Transmission owner
National Grid (England & Wales)
Connection type
Embedded (connects through the local distribution network)
NESO project status
Built

Connection site

The marker shows the connection substation, not the project itself, with the transmission network around it.

Projects connecting near Kemsley GSP Β· Grid map

Other projects at Kemsley GSP

Source: NESO Transmission Entry Capacity (TEC) register, downloaded 8 November 2026. Contains data from NESO, licensed under the NESO Open Data Licence. Report a problem