Grid infrastructure › Connection queue › Interconnector
INTERCONNECTOR · NGETNeuConnect Interconnector
NeuConnect Interconnector is a 1.5 GW interconnector project under construction or commissioning, connecting to the National Grid (England & Wales) network at Wallend 400kV Substation, with capacity due from July 2027. The connection agreement is held by Neuconnect Britain Ltd.
Project stageUnder construction
- Planning (completed)
- Consented (completed)
- Construction (current stage)
- OperatingFrom Jul 2027 (not yet reached)
- Closed (not yet reached)
Connection details
- NESO project number
- PRO-001288
- Customer
- Neuconnect Britain Ltd
- Technology
- Interconnector
- Export capacity
- 1.5 GW
- Import capacity
- 1.4 GW
- Change in this agreement
- +1.5 GW
- Capacity effective from
- 7 July 2027
- Connection site
- Wallend 400kV Substation
- Transmission owner
- National Grid (England & Wales)
- Connection type
- Interconnector
- NESO project status
- Under Construction/Commissioning
- Connections reform gate
- Gate 2
Connection site
The connection site could not be placed on the map.
Other projects at Wallend 400kV Substation
Source: NESO interconnector register, downloaded 8 November 2026. Contains data from NESO, licensed under the NESO Open Data Licence. Report a problem