Grid infrastructure βΊ Connection queue βΊ Interconnector
INTERCONNECTOR Β· SHETNorthConnect
NorthConnect is a 1.4 GW interconnector project in planning, connecting to the SSEN Transmission (north Scotland) network at Peterhead 400kV Substation, with capacity due from March 2030. The connection agreement is held by Northconnect Limited.
- Planning (current stage)
- Consented (not yet reached)
- Construction (not yet reached)
- OperatingFrom Mar 2030 (not yet reached)
- Closed (not yet reached)
Scoping and awaiting consents are both shown as planning. A connection agreement does not mean the project will be built: many queue projects never reach construction.
Connection details
- NESO project number
- PRO-001285
- Customer
- Northconnect Limited
- Technology
- Interconnector
- Export capacity
- 1.4 GW
- Import capacity
- 1.4 GW
- Change in this agreement
- +1.4 GW
- Capacity effective from
- 1 March 2030
- Connection site
- Peterhead 400kV Substation
- Transmission owner
- SSEN Transmission (north Scotland)
- Connection type
- Interconnector
- NESO project status
- Scoping
Connection site
The marker shows the connection substation, not the project itself, with the transmission network around it.
Other projects at Peterhead 400kV Substation
Source: NESO interconnector register, downloaded 8 November 2026. Contains data from NESO, licensed under the NESO Open Data Licence. Report a problem