Grid infrastructure βΊ Connection queue βΊ Battery storage
BATTERY STORAGE Β· SHETJamesfield Farm Phase 2 Battery Storage
Jamesfield Farm Phase 2 Battery Storage is a 19 MW battery storage project built and connected, connecting to the SSEN Transmission (north Scotland) network at Abernethy GSP. The connection agreement is held by Harmony Jf Limited.
Connection details
- NESO project number
- PRO-001236
- Customer
- Harmony Jf Limited
- Technology
- Energy Storage System
- Total capacity
- 19 MW
- Already connected
- 19 MW
- Connection site
- Abernethy GSP
- Transmission owner
- SSEN Transmission (north Scotland)
- Connection type
- Embedded (connects through the local distribution network)
- NESO project status
- Built
Connection site
The marker shows the connection substation, not the project itself, with the transmission network around it.
Other projects at Abernethy GSP
Source: NESO Transmission Entry Capacity (TEC) register, downloaded 8 November 2026. Contains data from NESO, licensed under the NESO Open Data Licence. Report a problem