Grid infrastructure › Connection queue › Battery storage

BATTERY STORAGE · NGET

Sundon

Sundon is a 50 MW battery storage project under construction or commissioning, connecting to the National Grid (England & Wales) network at Sundon 400kV Substation, with capacity due from April 2027. The connection agreement is held by Sundon Battery Storage Limited.

Project stageUnder construction
  1. Planning (completed)
  2. Consented (completed)
  3. Construction (current stage)
  4. OperatingFrom Apr 2027 (not yet reached)
  5. Closed (not yet reached)

Connection details

NESO project number
PRO-001132
Customer
Sundon Battery Storage Limited
Technology
Energy Storage System
Total capacity
50 MW
Change in this agreement
+50 MW
Capacity effective from
30 April 2027
Connection site
Sundon 400kV Substation
Transmission owner
National Grid (England & Wales)
Connection type
Direct connection to the transmission network
NESO project status
Under Construction/Commissioning
Connections reform gate
Gate 2

Connection site

The marker shows the connection substation, not the project itself, with the transmission network around it.

Projects connecting near Sundon · Grid map

Other projects at Sundon 400kV Substation

Source: NESO Transmission Entry Capacity (TEC) register, downloaded 8 November 2026. Contains data from NESO, licensed under the NESO Open Data Licence. Report a problem