🔌 EV Partnership Switch to Octopus Energy & unlock exclusive smart EV charging rates Find out more → Skip to main content

Grid infrastructure › Connection queue › Onshore wind

ONSHORE WIND · SHET

Hollandmey Renewable Energy Development

Hollandmey Renewable Energy Development is a 50 MW onshore wind project consented, connecting to the SSEN Transmission (north Scotland) network at Hollandmey Renewable Energy Development132/33kV Substation, with capacity due from May 2030. The connection agreement is held by Scottish Power Renewables (UK) Limited.

Project stageConsented
  1. Planning (completed)
  2. Consented (current stage)
  3. Construction (not yet reached)
  4. OperatingFrom May 2030 (not yet reached)
  5. Closed (not yet reached)

Connection details

NESO project number
PRO-001094
Customer
Scottish Power Renewables (UK) Limited
Technology
Wind Onshore
Total capacity
50 MW
Change in this agreement
+50 MW
Capacity effective from
31 May 2030
Connection site
Hollandmey Renewable Energy Development132/33kV Substation
Transmission owner
SSEN Transmission (north Scotland)
Connection type
Direct connection to the transmission network
NESO project status
Consents Approved

Connection site

The connection site could not be placed on the map.

Projects connecting near Hollandmey Renewable Energy Development · Grid map

Source: NESO Transmission Entry Capacity (TEC) register, downloaded 8 November 2026. Contains data from NESO, licensed under the NESO Open Data Licence. Report a problem