Grid infrastructure › Connection queue › Onshore wind
ONSHORE WIND · SHETHollandmey Renewable Energy Development
Hollandmey Renewable Energy Development is a 50 MW onshore wind project consented, connecting to the SSEN Transmission (north Scotland) network at Hollandmey Renewable Energy Development132/33kV Substation, with capacity due from May 2030. The connection agreement is held by Scottish Power Renewables (UK) Limited.
Project stageConsented
- Planning (completed)
- Consented (current stage)
- Construction (not yet reached)
- OperatingFrom May 2030 (not yet reached)
- Closed (not yet reached)
Connection details
- NESO project number
- PRO-001094
- Customer
- Scottish Power Renewables (UK) Limited
- Technology
- Wind Onshore
- Total capacity
- 50 MW
- Change in this agreement
- +50 MW
- Capacity effective from
- 31 May 2030
- Connection site
- Hollandmey Renewable Energy Development132/33kV Substation
- Transmission owner
- SSEN Transmission (north Scotland)
- Connection type
- Direct connection to the transmission network
- NESO project status
- Consents Approved
Connection site
The connection site could not be placed on the map.
Projects connecting near Hollandmey Renewable Energy Development · Grid map
Source: NESO Transmission Entry Capacity (TEC) register, downloaded 8 November 2026. Contains data from NESO, licensed under the NESO Open Data Licence. Report a problem