ONSHORE WIND Β· SHETDell Wind Farm
Dell Wind Farm is a 50 MW onshore wind project consented, connecting to the SSEN Transmission (north Scotland) network at Dell 132kV Substation, with capacity due from April 2030. The connection agreement is held by Dell Wind Farm Limited.
Project stageConsented
- Planning (completed)
- Consented (current stage)
- Construction (not yet reached)
- OperatingFrom Apr 2030 (not yet reached)
- Closed (not yet reached)
Connection details
- NESO project number
- PRO-001012
- Customer
- Dell Wind Farm Limited
- Technology
- Wind Onshore
- Total capacity
- 50 MW
- Change in this agreement
- +50 MW
- Capacity effective from
- 1 April 2030
- Connection site
- Dell 132kV Substation
- Transmission owner
- SSEN Transmission (north Scotland)
- Connection type
- Direct connection to the transmission network
- NESO project status
- Consents Approved
Connection site
The connection site could not be placed on the map.