Grid infrastructure › Connection queue › Onshore wind
ONSHORE WIND · SPTEuchanhead Wind Farm
Euchanhead Wind Farm is a 112 MW onshore wind project in planning, connecting to the SP Transmission (south Scotland) network at Euchanhead 132kV Substation, with capacity due from October 2030. The connection agreement is held by Scottish Power Renewables (UK) Limited.
- Planning (current stage)
- Consented (not yet reached)
- Construction (not yet reached)
- OperatingFrom Oct 2030 (not yet reached)
- Closed (not yet reached)
Scoping and awaiting consents are both shown as planning. A connection agreement does not mean the project will be built: many queue projects never reach construction.
Connection details
- NESO project number
- PRO-001011
- Customer
- Scottish Power Renewables (UK) Limited
- Technology
- Wind Onshore
- Total capacity
- 112 MW
- Change in this agreement
- +112 MW
- Capacity effective from
- 29 October 2030
- Connection site
- Euchanhead 132kV Substation
- Transmission owner
- SP Transmission (south Scotland)
- Connection type
- Direct connection to the transmission network
- NESO project status
- Awaiting Consents
Connection site
The connection site could not be placed on the map.
Source: NESO Transmission Entry Capacity (TEC) register, downloaded 8 November 2026. Contains data from NESO, licensed under the NESO Open Data Licence. Report a problem