Grid infrastructure βΊ Connection queue βΊ Onshore wind
ONSHORE WIND Β· SPTHare Craig Wind Farm
Hare Craig Wind Farm is a 46 MW onshore wind project in planning, connecting to the SP Transmission (south Scotland) network at Hare Craig 33kV Substation, with capacity due from October 2028. The connection agreement is held by Hare Craig Windfarm LLP.
- Planning (current stage)
- Consented (not yet reached)
- Construction (not yet reached)
- OperatingFrom Oct 2028 (not yet reached)
- Closed (not yet reached)
Scoping and awaiting consents are both shown as planning. A connection agreement does not mean the project will be built: many queue projects never reach construction.
Connection details
- NESO project number
- PRO-000940
- Customer
- Hare Craig Windfarm LLP
- Technology
- Wind Onshore
- Total capacity
- 46 MW
- Change in this agreement
- +46 MW
- Capacity effective from
- 31 October 2028
- Connection site
- Hare Craig 33kV Substation
- Transmission owner
- SP Transmission (south Scotland)
- Connection type
- Direct connection to the transmission network
- NESO project status
- Awaiting Consents
Connection site
The connection site could not be placed on the map.
Source: NESO Transmission Entry Capacity (TEC) register, downloaded 8 November 2026. Contains data from NESO, licensed under the NESO Open Data Licence. Report a problem