Grid infrastructure › Connection queue › Onshore wind
ONSHORE WIND · SHETHill of Towie 2 Wind Farm
Hill of Towie 2 Wind Farm is a 36 MW onshore wind project consented, connecting to the SSEN Transmission (north Scotland) network at Keith 2 132/33kV GSP Substation, with capacity due from June 2030. The connection agreement is held by Greenhills 1 Limited.
Project stageConsented
- Planning (completed)
- Consented (current stage)
- Construction (not yet reached)
- OperatingFrom Jun 2030 (not yet reached)
- Closed (not yet reached)
Connection details
- NESO project number
- PRO-000938
- Customer
- Greenhills 1 Limited
- Technology
- Wind Onshore
- Total capacity
- 36 MW
- Change in this agreement
- +36 MW
- Capacity effective from
- 1 June 2030
- Connection site
- Keith 2 132/33kV GSP Substation
- Transmission owner
- SSEN Transmission (north Scotland)
- Connection type
- Embedded (connects through the local distribution network)
- NESO project status
- Consents Approved
- Connections reform gate
- Gate 2
Connection site
The marker shows the connection substation, not the project itself, with the transmission network around it.
Other projects at Keith 2 132/33kV GSP Substation
Source: NESO Transmission Entry Capacity (TEC) register, downloaded 8 November 2026. Contains data from NESO, licensed under the NESO Open Data Licence. Report a problem