Grid infrastructure β€Ί Connection queue β€Ί Onshore wind

ONSHORE WIND Β· SHET

Mossy Hill Wind Farm

Mossy Hill Wind Farm is a 40 MW onshore wind project consented, connecting to the SSEN Transmission (north Scotland) network at Mossy Hill 132kV Substation, with capacity due from June 2029. The connection agreement is held by Mossy Hill Shetland Limited.

Project stageConsented
  1. Planning (completed)
  2. Consented (current stage)
  3. Construction (not yet reached)
  4. OperatingFrom Jun 2029 (not yet reached)
  5. Closed (not yet reached)

Connection details

NESO project number
PRO-000461
Customer
Mossy Hill Shetland Limited
Technology
Demand, Wind Onshore
Total capacity
40 MW
Change in this agreement
+40 MW
Capacity effective from
29 June 2029
Connection site
Mossy Hill 132kV Substation
Transmission owner
SSEN Transmission (north Scotland)
Connection type
Direct connection to the transmission network
NESO project status
Consents Approved
Connections reform gate
Gate 2

Connection site

The connection site could not be placed on the map.

Projects connecting near Mossy Hill Β· Grid map

Source: NESO Transmission Entry Capacity (TEC) register, downloaded 8 November 2026. Contains data from NESO, licensed under the NESO Open Data Licence. Report a problem