🔌 EV Partnership Switch to Octopus Energy & unlock exclusive smart EV charging rates Find out more → Skip to main content

Grid infrastructure › Connection queue › Offshore wind

OFFSHORE WIND · NGET

Hornsea Power Station 2C

Hornsea Power Station 2C is a 440 MW offshore wind project built and connected, connecting to the National Grid (England & Wales) network at Hornsea Power Station 2C Offshore platform Substation. The connection agreement is held by Sonningmay Wind Limited.

Project stageOperating
  1. Planning (completed)
  2. Consented (completed)
  3. Construction (completed)
  4. Operating (current stage)
  5. Closed (not yet reached)

Connection details

NESO project number
PRO-000335
Customer
Sonningmay Wind Limited
Technology
Wind Offshore
Total capacity
440 MW
Already connected
440 MW
Connection site
Hornsea Power Station 2C Offshore platform Substation
Transmission owner
National Grid (England & Wales)
Connection type
Direct connection to the transmission network
NESO project status
Built

Connection site

The connection site could not be placed on the map.

Projects connecting near Hornsea Power Station · Grid map

Source: NESO Transmission Entry Capacity (TEC) register, downloaded 8 November 2026. Contains data from NESO, licensed under the NESO Open Data Licence. Report a problem