Hornsea Power Station 2B

Hornsea Power Station 2B is a 440 MW offshore wind project built and connected, connecting to the National Grid (England & Wales) network at Hornsea Platform 2B Offshore Substation. The connection agreement is held by Soundmark Wind Limited.

Project stageOperating
  1. Planning (completed)
  2. Consented (completed)
  3. Construction (completed)
  4. Operating (current stage)
  5. Closed (not yet reached)

Connection details

NESO project number
PRO-000334
Customer
Soundmark Wind Limited
Technology
Wind Offshore
Total capacity
440 MW
Already connected
440 MW
Connection site
Hornsea Platform 2B Offshore Substation
Transmission owner
National Grid (England & Wales)
Connection type
Direct connection to the transmission network
NESO project status
Built

Connection site

The connection site could not be placed on the map.

Projects connecting near Hornsea Platform · Grid map

Source: NESO Transmission Entry Capacity (TEC) register, downloaded 8 November 2026. Contains data from NESO, licensed under the NESO Open Data Licence. Report a problem