Glenmuckloch Pumped Storage is a 210 MW hydro and pumped storage project consented, connecting to the SP Transmission (south Scotland) network at Glenmuckloch 132kV Substation, with capacity due from May 2029. The connection agreement is held by Glenmuckloch Pumped Storage Hydro Limited.
Project stageConsented
- Planning (completed)
- Consented (current stage)
- Construction (not yet reached)
- OperatingFrom May 2029 (not yet reached)
- Closed (not yet reached)
Connection details
- NESO project number
- PRO-000299
- Customer
- Glenmuckloch Pumped Storage Hydro Limited
- Technology
- Pump Storage
- Total capacity
- 210 MW
- Change in this agreement
- +210 MW
- Capacity effective from
- 18 May 2029
- Connection site
- Glenmuckloch 132kV Substation
- Transmission owner
- SP Transmission (south Scotland)
- Connection type
- Direct connection to the transmission network
- NESO project status
- Consents Approved
Connection site
The connection site could not be placed on the map.
Other projects at Glenmuckloch 132kV Substation
Source: NESO Transmission Entry Capacity (TEC) register, downloaded 8 November 2026. Contains data from NESO, licensed under the NESO Open Data Licence. Report a problem