Grid infrastructure βΊ Connection queue βΊ Interconnector
INTERCONNECTOR Β· NGETGreenlink
Greenlink is a 524 MW interconnector project built and connected, connecting to the National Grid (England & Wales) network at Pembroke 400kV Substation. The connection agreement is held by Greenlink Interconnector Limited.
Connection details
- NESO project number
- PRO-000279
- Customer
- Greenlink Interconnector Limited
- Technology
- Interconnector
- Export capacity
- 524 MW
- Import capacity
- 504 MW
- Already connected
- 524 MW
- Connection site
- Pembroke 400kV Substation
- Transmission owner
- National Grid (England & Wales)
- Connection type
- Interconnector
- NESO project status
- Built
Connection site
The marker shows the connection substation, not the project itself, with the transmission network around it.
Other projects at Pembroke 400kV Substation
- Pembroke Power StationHydro and pumped storage Β· 2.2 GW Β· Built
- Pembroke BESSBattery storage Β· 350 MW Β· Consents Approved
- Llywelyn Floating Offshore Wind FarmOffshore wind Β· 300 MW Β· Scoping
- Valorous Offshore Wind FarmOffshore wind Β· 300 MW Β· Scoping
- Pembroke BESSBattery storage Β· 285 MW Β· Consents Approved
- Lambeeth 240MWBattery storage Β· 240 MW Β· Scoping
- LlΕ·r Floating WindOffshore wind Β· 200 MW Β· Scoping
- Pembroke BESS and Solar StationSolar + storage Β· 100 MW Β· Awaiting Consents
Source: NESO interconnector register, downloaded 8 November 2026. Contains data from NESO, licensed under the NESO Open Data Licence. Report a problem