JG Pears is a 450 MW solar + storage project built and connected, connecting to the National Grid (England & Wales) network at High Marnham 275kV Substation. The connection agreement is held by Jg Pears Grid Connection Limited.

Project stageOperating
  1. Planning (completed)
  2. Consented (completed)
  3. Construction (completed)
  4. OperatingOct 2033 (current stage)
  5. Closed (not yet reached)

Connection details

NESO project number
PRO-000250
Customer
Jg Pears Grid Connection Limited
Technology
CHP (Combined Heat and Power), Energy Storage System, PV Array (Photo Voltaic/solar), Wind Onshore
Total capacity
450 MW
Already connected
30 MW
Change in this agreement
+420 MW
Capacity effective from
31 October 2033
Connection site
High Marnham 275kV Substation
Transmission owner
National Grid (England & Wales)
Connection type
Direct connection to the transmission network
NESO project status
Built

Connection site

The marker shows the connection substation, not the project itself, with the transmission network around it.

Projects connecting near High Marnham · Grid map

Source: NESO Transmission Entry Capacity (TEC) register, downloaded 8 November 2026. Contains data from NESO, licensed under the NESO Open Data Licence. Report a problem