OFFSHORE WIND · OFTOWalney II Offshore Wind Farm
Walney II Offshore Wind Farm is a 182 MW offshore wind project built and connected, connecting to the Offshore transmission owner network at Walney 2 33/132kV Substation. The connection agreement is held by Walney (UK) Offshore Windfarms Limited.
Connection details
- NESO project number
- PRO-000222
- Customer
- Walney (UK) Offshore Windfarms Limited
- Technology
- Wind Offshore
- Total capacity
- 182 MW
- Already connected
- 182 MW
- Connection site
- Walney 2 33/132kV Substation
- Transmission owner
- Offshore transmission owner
- Connection type
- Direct connection to the transmission network
- NESO project status
- Built