Fort Dunlop

Fort Dunlop is a 99 MW gas project built and connected, connecting to the National Grid (England & Wales) network at Dunlop 132kV Substation. The connection agreement is held by Whitetower Energy Limited.

Project stageOperating
  1. Planning (completed)
  2. Consented (completed)
  3. Construction (completed)
  4. Operating (current stage)
  5. Closed (not yet reached)

Connection details

NESO project number
PRO-000160
Customer
Whitetower Energy Limited
Technology
OCGT (Open Cycle Gas Turbine)
Total capacity
99 MW
Already connected
99 MW
Connection site
Dunlop 132kV Substation
Transmission owner
National Grid (England & Wales)
Connection type
Embedded (connects through the local distribution network)
NESO project status
Built

Connection site

The marker shows the place the connection site is named after, not the project itself, with the transmission network around it.

Projects connecting near Dunlop Β· Grid map