Farr Wind Farm - Tomatin

Farr Wind Farm - Tomatin is a 92 MW onshore wind project built and connected, connecting to the SSEN Transmission (north Scotland) network at Beauly GSP. The connection agreement is held by Farr Windfarm Limited.

Project stageOperating
  1. Planning (completed)
  2. Consented (completed)
  3. Construction (completed)
  4. Operating (current stage)
  5. Closed (not yet reached)

Connection details

NESO project number
PRO-000156
Customer
Farr Windfarm Limited
Technology
Wind Onshore
Total capacity
92 MW
Already connected
92 MW
Connection site
Beauly GSP
Transmission owner
SSEN Transmission (north Scotland)
Connection type
Direct connection to the transmission network
NESO project status
Built

Connection site

The marker shows the connection substation, not the project itself, with the transmission network around it.

Projects connecting near Beauly GSP Β· Grid map

Source: NESO Transmission Entry Capacity (TEC) register, downloaded 8 November 2026. Contains data from NESO, licensed under the NESO Open Data Licence. Report a problem