HYDRO AND PUMPED STORAGE · SHETCeannacroc (part of the Moriston Cascade)
Ceannacroc (part of the Moriston Cascade) is a 20 MW hydro and pumped storage project built and connected, connecting to the SSEN Transmission (north Scotland) network at Ceannacroc GSP. The connection agreement is held by Sse Generation Limited.
Connection details
- NESO project number
- PRO-000070
- Customer
- Sse Generation Limited
- Technology
- Hydro
- Total capacity
- 20 MW
- Already connected
- 20 MW
- Connection site
- Ceannacroc GSP
- Transmission owner
- SSEN Transmission (north Scotland)
- Connection type
- Embedded (connects through the local distribution network)
- NESO project status
- Built
Connection site
The marker shows the connection substation, not the project itself, with the transmission network around it.
Source: NESO Transmission Entry Capacity (TEC) register, downloaded 8 November 2026. Contains data from NESO, licensed under the NESO Open Data Licence. Report a problem