United States › Power plants › Battery storage › Missouri
BATTERY STORAGE · SOLAR FARMSScopus Solar
Scopus Solar is a 400 MW planned power plant in Bollinger County, Missouri, operated by Vesper Energy Development LLC.
Plant statusIn planning
- Planning (current stage)
- Consented (not yet reached)
- Construction (not yet reached)
- OperatingTarget Dec 2027 (not yet reached)
- Closed (not yet reached)
Planned start of operation reported to EIA: Dec 2027.
Generators
Each generating unit EIA lists at this plant.
| Unit | Technology | Capacity | Status |
|---|---|---|---|
| SCPSB | Batteries | 200 MW | Planned, approvals not yet sought |
| SCPSR | Solar Photovoltaic | 200 MW | Planned, approvals not yet sought |
Plant details
- Operator
- Vesper Energy Development LLC
- Location
- Bollinger County, Missouri
- Balancing authority
- MISO
- Sector
- IPP Non-CHP
- Capacity
- Planned: 400 MW
- EIA plant ID
- 68031
Location
37.3922, -89.8993
Nearby power plants
- Jackson (MO)Oil-fired power plants · 26.3 MW · 13.1 mi
- Delta Bobcat SolarSolar farms · 200 MW · 15.4 mi
- Cape Girardeau Renewable Energy CenterSolar farms · 1.2 MW · 21.1 mi
- Fredericktown Energy CenterGas power plants · 27.6 MW · 26.1 mi
- Kelso SolarSolar farms · 200 MW · 31.5 mi
- Kelso 2 SolarSolar farms · 149 MW · 31.5 mi
- EssexGas power plants · 121 MW · 36.3 mi
- Wild Cat Solar 22 LLCSolar farms · 2.3 MW · 37.5 mi
- Farmington Solar FarmSolar farms · 2.5 MW · 38.3 mi
- Sikeston Power StationCoal power plants · 261 MW · 38.6 mi
Source: U.S. Energy Information Administration, Form EIA-860M, September 2026. Planned dates are targets reported by the developer and often change. Report a problem